ACG Metals (LON: ACG) said Tuesday it plans to buy Blue Moon Metals' Norwegian assets in a $220-million all-share deal, adding an EU-designated strategic copper project to its Turkish mine, according to MINING.COM. The acquisition would combine mining operations in the Arctic and southern Türkiye and give the London-listed miner a foothold as a European copper producer. The rest of today's news shows how much stands between a project and first production. Regulators, permits, contractor workforces and financing all appear in the announcements below.
ACG Metals: $220-Million All-Share Bid for Blue Moon Norway
ACG would acquire Blue Moon Norway AS, which includes a 94.52% stake in the Nussir copper project in northern Norway, MINING.COM reported. The deal would sit alongside ACG's Gediktepe mine in Türkiye. Combined annual production is forecast to exceed 50,000 tonnes of copper equivalent by 2029. ACG chairman and CEO Artem Volynets said in a statement that the deal "creates a fast-growing European copper champion with industry-leading free cash flow margins".
Nussir, near Hammerfest in Norway's northern Finnmark region, is fully permitted and under construction, with first copper concentrate expected in the first half of 2028. The European Union has designated it a strategic project under its Critical Raw Materials Act. A feasibility study outlines a 13-year mine life extending to 2041.
On price, the transaction values Blue Moon Norway at about 59% of its $375-million broker consensus net asset value. ACG estimates that $84 million of Nussir's initial capital expenditure will have been spent by completion, leaving $126 million to fund. The company expects to close by Nov. 30, subject to shareholder and regulatory approvals, and the agreement has a Dec. 15 long-stop date.
MMG and Anglo American: Brazilian Nickel Deal Pushed Back
MMG (HKEX: 1208) and Anglo American (LON: AAL) extended the deadline for their $500-million Brazilian nickel deal by two months, MINING.COM reported. European Union regulators are scrutinizing its potential impact on the region's stainless steel industry. The companies moved the long-stop date from Oct. 31 to Dec. 31, 2026 rather than terminate the transaction after failing to secure regulatory approval.
The European Commission has opened an in-depth Phase II investigation and is expected to issue its decision by Dec. 21. Its main concern is whether the acquisition could let MMG divert Brazilian ferronickel away from Europe. Reuters reported, as relayed by MINING.COM, that Anglo American would likely close its Brazilian nickel operation if the EU blocks the deal.
Gold Fields: Environmental Authorization for Windfall
Gold Fields (NYSE, JSE: GFI) has received a key environmental authorization for its high-grade Windfall gold project in Quebec, MINING.COM reported. The approval clears a major regulatory hurdle as the company prepares for a final investment decision. The company is targeting that decision by February 2027. Once fully ramped up, the mine is expected to produce about 300,000 oz. of gold annually. The proposed mine is a $1.9-billion project.
The certificate allows construction to proceed subject to regulatory conditions, but Gold Fields must still secure a mining lease and secondary permits. The authorization follows a setback in late September, when the company suspended underground development at Windfall after an exploration-work permit expired.
Standard Lithium: Year-End Decision on Arkansas Project
Standard Lithium (TSXV, NYSE-A: SLI) is targeting a year-end investment decision on its $1.45-billion capex South West Arkansas (SWA) project, MINING.COM reported. The project would become the first large-scale lithium producing site in the oil-rich Smackover Formation. Standard and partner Equinor aim to start construction early in 2027 and begin production in 2029, subject to the investment decision and financing. Standard's Jesse Edmondson said: "We're very confident that we'll be under construction on that project very early next year."
The first stage is designed to produce 22,500 tonnes annually of battery-grade lithium carbonate over a modelled 20-year operating life, with expansion potential. Smackover Lithium has offtake deals covering up to 20,000 tonnes of lithium carbonate annually, or about 89% of planned output.
Financing is the open item. In December 2025, Smackover Lithium said it had received indications of interest for more than $1 billion in project debt financing for the first stage from export credit agencies. Those expressions were not financing commitments, and talks are ongoing. CRU analyst Cameron Hughes said: "DLE is still a fairly novel technology."