Lithium Americas (TSX, NYSE: LAC) has raised the estimated cost of the first phase of its Thacker Pass lithium project in Nevada by 31% to $3.83 billion, citing rising labour, construction and logistics expenses, MINING.COM reported. The revision shows how construction-cost inflation is reaching new US mines, even for a project with a US Department of Energy loan and General Motors as its joint venture partner. Elsewhere in today's announcements, Endeavour Mining took a similar budget hit in West Africa, while other developers secured debt, partners and drill results.
Lithium Americas: Thacker Pass Phase 1 Budget Rises
The revised budget adds $895 million in capital costs and increases the project's funding requirement by about $995 million, Lithium Americas said Wednesday. Higher labour installation rates for piping, steel and equipment accounted for $245 million of the increase, according to MINING.COM, while tariffs and logistics added approximately $100 million.
The company expects to cover the additional amount through company contributions and available reserves under its DOE loan. It now expects to spend between $1.7 billion and $2 billion on Phase 1 in 2026, compared with its previous forecast of $1.3 billion to $1.6 billion. Lithium Americas held about $1.3 billion in cash and restricted cash as of Sept. 30, including approximately $360 million at the Thacker Pass joint venture with General Motors (NYSE: GM).
The market reacted negatively. Shares fell almost 8% to C$2.48 apiece in early Toronto trading, leaving a market capitalization of nearly C$544 million ($382 million). The schedule has not changed. Lithium Americas continues to target commercial production in 2028, with Phase 1 designed to produce 40,000 tonnes of battery-grade lithium carbonate annually at full capacity. CEO Jonathan Evans said: "Phase 1 is advancing toward peak construction activity by year end 2026, with mechanical completion targeted for late 2027."
Endeavour Mining: Assafou Approved Despite Higher Budget
Endeavour Mining (LON, TSX: EDV) has approved construction of its $1.2-billion Assafou gold project in Côte d'Ivoire, targeting first production in the first half of 2029. The development budget has risen by $139 million, or 13%, from the $1.06 billion estimated in the feasibility study. Increased land and crop compensation accounts for approximately 60% of the increase, following consultations with local authorities and communities.
A definitive feasibility study released in April outlined average production of 320,000 oz. of gold annually at all-in sustaining costs of $1,026 per oz. during the first eight years. The project has an initial mine life of 16 years and a processing plant designed to handle 5 million tonnes of ore annually. Endeavour has awarded the engineering, procurement and construction management contract to Lycopodium and reached an agreement in principle on the terms of its mining convention with Côte d'Ivoire.
The group's third-quarter results gave it financial room to proceed. They showed record free cash flow of $1.02 billion for the first nine months of 2026, up 50% from a year earlier. Endeavour ended September with $263 million in net cash after reducing gross debt by $412 million. The weaker side of the report is operational. Gold production totalled 820,000 oz. through September, down 10% year over year, at AISC of $1,866 per oz. The Mana mine in Burkina Faso remains a concern after underground mining was suspended following access-ramp subsidence in October, with processing not expected to resume until the second quarter of 2027.
Minerals 260: Bullabulling Gets Bank Debt Without Hedging
Minerals 260 (ASX: MI6) has secured A$410 million (C$399 million) in bank debt for its Bullabulling gold project in Western Australia, with no requirement to lock in future gold prices. ANZ, National Australia Bank and Société Générale have committed A$335 million for project financing and A$75 million for working capital.
Managing Director Luke McFadyen said securing credit approval before completing the feasibility study reflects "the high quality, high margin and long-life aspects of Bullabulling." Several conditions remain: completing the definitive feasibility study, final due diligence, loan documents and an agreement with Franco-Nevada governing creditors' rights. The construction decision and final loan conditions are due early next year, and the first debt drawdown is expected late next year.
Franco-Nevada agreed in September to provide another $170 million in royalty funding and buy $30 million of Minerals 260 shares. That brings its aggregate backing to $420 million and increases its gross royalty on Bullabulling to 3.9% from 2.45%. Bullabulling, 65 km from Kalgoorlie, has 140 million indicated tonnes at 0.98 gram per tonne gold for 4.4 million oz., plus 51 million inferred tonnes at 1 gram gold for 1.7 million oz., according to a resource issued in July. BMO Capital Markets initiated coverage on Nov. 10 with an outperform rating and a A$1.75 share-price target.