Lithium prices have fallen sharply since May, when they touched their highest level since September 2023, Reuters reported. Expectations for a surplus have hardened as new mines opened and idled operations restarted. LIT, the lithium and battery ETF, dropped 4.33% to $51.98 at Friday's close.
Yet in Saskatchewan, a production well is flowing. In Alberta, a demonstration plant has moved to its next phase. In Hai Phong, a rare earth refinery is under construction. And in Harare, the finance minister has rewritten the export tax code. None of this is a bet on price. Each project exists because a government decided to pay for, protect or require processing capacity, and that is where the midstream is now being built.
Canada's brine, on the state's dime
Prairie Lithium has brought its first surface brine from a production well at Pad #1, meeting a milestone it had set for the fourth quarter of 2026, Mining Technology reported. The well was re-entered, perforated and swabbed to reach production zones in the Duperow Formation. The pad also holds earlier production and disposal wells and a commercial-scale four-column direct lithium extraction unit. Phase 1 is supported by C$6.3m in interest-free financing from the Canadian government through Prairies Economic Development Canada. Next come metallurgical testing on the recovered brine and planning for lithium chloride concentration equipment.
E3 Lithium's Clearwater project, east of Olds, Alberta, shows the same pattern with more friction. The company said it has completed Phase 2 of its Demonstration Facility and started Phase 3, Bnnbloomberg reported. Its full-scale well pair has produced over 80,000 m³ of brine from the Leduc reservoir. Phase 3 recommissions a 30-column extraction system meant to yield battery-grade lithium carbonate. Phase 3 and front-end engineering are backed by up to $36.5 million in non-repayable funding from Natural Resources Canada's Global Partnerships Initiative.
Private capital has not matched that confidence. E3 lists a Class III cost estimate and binding offtake agreements among the drivers that must come before project financing. Phase 2 ran long because the facility needed adjustments and repairs, which pushes engineering deliverables into 2027. The Alberta Energy Regulator has sent the Central Process Facility's D056 permit application to a formal hearing. The company also concedes that extraction technologies like its own have not been proven on a commercial scale or on its brine.
CEO Chris Doornbos stays upbeat. "Market fundamentals for lithium remain strong, with significant projected demand growth matching E3's expected timeline for commissioning our commercial facility.," he said. Fastmarkets analyst Connor Watts is less sure about who is propping up the price. "The Chinese utility and commercial vehicle industry isn't large enough to be singularly supporting lithium prices at this moment.," he said.
A tax code as a refinery
Zimbabwe makes the argument without a single well. Finance Minister Mthuli Ncube said on Nov 19 that the country will tax lithium concentrate exports on the value of the lithium sulphate they could yield, not on the concentrate's selling price, Zimlive reported, citing Reuters. For export tax purposes, benchmark-grade 6 percent concentrate converts at five tons of concentrate to one ton of sulphate. Sulphate exports keep a zero tax rate.
The message to miners is plain: ship rock and pay, or refine at home and don't. The country has Africa's largest lithium output, and an industry report cited by Reuters projects sulphate output of 208,000 metric tons in 2027 as new plants come online. The same report has concentrate rising to 2.3 million tons in 2027 from a projected 2.2 million tons this year. Ncube added that mining companies, government entities and other large businesses must source at least 15 percent of their inputs from local manufacturers.