Texas Is Where AI Needs Permission
Voters rejected data center projects in 40 of 41 local ballot measures. Texas, home to the biggest AI buildouts, now has to decide whether the constraint on AI is political rather than technical.
When Greg Abbott halted new data center connections to the Texas grid on August 3, ERCOT was tracking more than 400 gigawatts of projects waiting to plug in. That is roughly what it would take to power the entire US South, Reuters reported, as carried by KELO. The Republican governor was among the first in his party to shut that door. He did it with tens of billions of dollars of Texas projects already planned, and with doubts hanging over whether hundreds of millions in grid deposits would come back.
Three months on, the door he closed is a campaign issue, and the people who ran on it won. Governor-elect Gina Hinojosa, Reuters reported, "has rattled the state's data center industry with a campaign pledge to halt new projects." The question for the AI industry is no longer whether Texas can find the electrons. It is whether Texas will give permission to use them.
Forty of forty-one
The evidence that permission has become the scarcer input arrived on November 3. Voters in ten states decided 41 local ballot measures on data centers, which Duane Morris Government Strategies, writing on Statecapitallobbyist, called "the largest wave of such votes on record." Voters chose to limit data center development in 40 of them. The lone exception was Harwood, North Dakota, where voters rejected an added review requirement for industrial projects, 76 to 24.
Ohio supplied the starkest example. It had 21 of the 50 data center measures this year, and voters went against development in all 21. Eleven bans passed. In Wilmington, all four rezonings failed, 80 to 20. In Grove City, a rule requiring voter approval for large developments passed 55% to 45%. The Ohio Capital Journal counts at least 138 municipalities and townships with moratoriums, against 257 data centers in the state. Many of the ban measures share one threshold, 25 megawatts of peak demand, a line drawn to catch hyperscale sites.
Officials are paying too. Ballotpedia counted 42 recall efforts against 80 local officials over data center projects through early October. On Tuesday, voters removed seven more, including the mayor of Urbana, Ohio and three commissioners in Piqua.
An NBC News exit poll, relayed by TNW, found 76% of voters would oppose a new data center in their community. About 56% said AI and data centers were a crucial or major factor in their vote for Congress. Tom's Hardware attributes the anger to utility hikes, noise and the other burdens of power-hungry campuses, not to artificial intelligence in the abstract. The White House saw it coming. It asked hyperscalers, utilities and governors to sign a "ratepayer protection pledge." Trump even ordered data centers to pay energy dividends to host communities. Voters, Tom's Hardware reported, judged the moves too little, too late.
The Texas gap
Texas is the test because of scale. MIT Technology Review calls it the fastest-growing data center market in the US, with some of Big Tech's biggest AI buildouts under way. Democrats there won the Senate seat through James Talarico and the governor's race through Hinojosa. They will also control the state House for the first time in 24 years, after making data centers central to the campaign. Goldman Sachs chief economist Jan Hatzius wrote in a Wednesday note that states where Democrats are likely to restrict the industry further hold roughly 45% of planned US capacity. Texas alone is roughly 25%.
Abbott never issued a formal moratorium. Hinojosa has vowed to. Reuters noted that some of his measures expire soon, including the air permit ban and an audit due to conclude at the end of 2026. Her version would last until the state passes laws on water, electricity, air and property rights, Axios reported. TNW noted that the legislative session that could pass those laws ends in mid-2027. A pause with no obvious end date is the prospect developers face.
Austin McCarty, a government affairs adviser at K&L Gates, put it to Reuters this way: "It's a brand-new day in Texas for a ton of what was probably considered settled policy." He expects some projects to be delayed and some developers to leave the state. Others, he said, will rush to finish and power up before the restrictions land. Alpha Compute CEO Brittany Kaiser told Reuters that developers without signed contracts and financing are the likeliest to look at Canada, Mexico and Europe.
Sites already under construction, among them Stargate Frontier in Shackelford County and Nexus Hubbard, which is meant mostly to serve Anthropic, are the ones with the most to protect. Goldman also flagged that new Democratic governors in Texas, Georgia and Michigan could lead to legislation ending the industry's tax breaks.
Demand has not blinked
The market's first read was that scale is the shield. Amazon rose 8% and Microsoft 4% on Wednesday, while CoreWeave, which rents out AI computing power, fell 10%, TNW reported, relaying CNBC. Needham analyst Laura Martin wrote, per TNW, that higher regulatory barriers "entrench incumbents."
The mood was not uniformly sunny. PC Gamer Hardware reported that the Democratic wins and the votes to curb data centers had contributed to reduced confidence in AI stocks. Peter Boockvar of One Point BFG Wealth Partners said investors are now "questioning" the $1.2 trillion in AI capital spending Wall Street has forecast for next year.
Demand for the hardware inside the buildings has not softened. Counterpoint Research found a 369 percent year-over-year surge in DRAM revenue in the third quarter, and its research director MS Hwang said supply stays tight because major new fabs will not produce until 2028. Chips are scarce, and the shortage is easing slowly. Permission can vanish in a single election.
Washington will not settle this soon. MIT Technology Review says Democrats now hold both chambers, yet major federal energy legislation is unlikely while Trump is president. TNW noted Democrats take Congress in January without the two-thirds majorities needed to override a veto. That leaves the plans from Bernie Sanders and Alexandria Ocasio-Cortez for a nationwide moratorium as a statement of intent. The decisions fall to state capitols and county halls. The next two ballots are already scheduled: Clarksville, Arkansas votes on December 1 on bonds for named data center projects, and Mandan, North Dakota votes on December 15 on a 25-megawatt ban.
In August, the gate was the interconnection queue. Now it is the ballot box.